Stage 8 First Pass Yield was inconsistent and frequently below target, driving rework, delayed sign-off, and Damaged-in-Production scrap cost above budget.
Suppliers: Goods-in, upstream stages
Inputs: Torque wrench cal., operator competency, jig cal., DCR status
Process: Stage 8 assembly & PDI check
Outputs: Pass/fail status, fault category
Customers: PDI, downstream stages, end customer
Share of vans out of PDI that passed first time (A vans out divided by all vans out), added up across the days in each period. Source: Caravan Combined Performance Tracker, daily records from 1 Aug 2023 to 15 Jul 2025. The two 100% weeks are 2025 week 17 and week 30, each from 3 recorded days.
2 Y variables, 4 X variables tracked:
All faults logged on Avante, including on-the-spot corrections. Vans cannot receive final sign-off until every fault clears, which gives an auditable, gap-free measure of first-time pass performance.
Real monthly figures from the performance tracker. Months with fewer recorded days or vans are less reliable: Aug 2024 has 7 days, Jul 2025 has 12. One day in Aug 2024 was left out because it recorded more A vans than vans out.
Both top failure modes trace to torque discipline:
Both flagged with weak or no current detection control, so the action is to collect data.
Run your own analysis with the 5 Whys root cause tool.
Weekly FPY vs time: quadratic fit R² = 0.275. Time alone is a weak predictor, which suggests the process inputs above, not the passage of time, are the drivers.
Average Sep 2024 to Mar 2025, then July 2025 to the 15th. Individual weeks reached 100%. The tracker ends on 15 Jul 2025, so it does not show whether this held.
C&E matrix and PFMEA scoring shown here reflect the Green Belt project workup built from this data. The first pass yield figures on this page come from the Caravan Combined Performance Tracker and measure the whole line at PDI. Stage 8 end-of-line figures on the SQCDP dashboard come from a different source and have not been reconciled with these.